H Street reconstruction update for week of July 7-11

Y&K Excavation, Inc. has installed new service lines between 3rd Street and 5th Street on H Street. Water mains will be placed between 5th Street and 7th Street on H this week. Water shut offs are not anticipated this week. Residents will be notified in advance via door hangers on their front door, and in person if possible, if a water shut off will occur.

Storm drain construction will begin at 3rd Street this week.

All vehicles will need to remain off H Street between 3rd and 8th until further notice.

Your safety is a priority to us and we appreciate your patience during this construction period.

For more information about the H Street reconstruction project visit the project page at: https://cityofsalida.com/projects/h-street-reconstruction/