Wastewater Treatment Plant Upgrade

The City must resolve waste water treatment violations to avoid severe financial penalties and adverse environmental effects. The plant currently operates at a lower capacity than is permitted due to inefficiencies and does not meet ammonia limits currently imposed by the Colorado Department of Public Health and Environment. Built in 1956 and renovated in 1985, it does not have the components necessary to meet ammonia standards and to supply sufficient capacities for the communities served, Salida and Poncha Springs. The aging facility’s concrete and mechanical equipment is deteriorating, it lacks efficient energy conservation and is approaching the end of its service life.

During 2008, the City’s engineering firm completed a study of the wastewater treatment facility. Recommendations for a major upgrade of the facility were presented to the council in January 2009. The facility operates at a lower capacity than is permitted due to inefficiencies and it does not meet ammonia limits currently imposed by the Colorado Department of Public Health and Environment (CDPHE).  Built in 1956 and renovated in 1985, the facility does not have the components necessary to meet ammonia standards or to supply sufficient capacities for the communities served. The aging facility’s concrete and mechanical equipment has deteriorated; it lacks efficient energy conservation; and it is approaching the end of its service life. Salida must resolve its wastewater treatment violations to avoid severe financial penalties and adverse environmental effects to the Arkansas River where the effluent is discharged.

A number of presentations have been made to update council members and the public on the need for the upgrade and the cost of the project. In addition, the City was awarded a DOLA grant for $1.35 million. Approximately 90% of those funds were used in 2009 to begin purchasing the new equipment needed for the project.

Late in 2009, we began meeting with representatives from the USDA Rural Development about the remaining funding needed for the project. The USDA program requires the City to obtain interim financing during the construction period that is refinanced with a “permanent” federal loan once the project is completed. The USDA program presented an opportunity for additional grant funding and a below-market interest rate for the loan. Lower financing costs equate to a reduction in the overall project cost and lower rates for users of the sewer system.

The City’s engineers are finalizing the drawings and specifications with the USDA engineer. Bidding is expected to begin in mid September. The earliest we expect to award the project and begin construction is early November.

Most Recent

Wastewater Treatment Plant Update

Wastewater Treatment Plant construction began September 28, 2011 with mobilization, excavation and demolition of old equipment. During the last four months, 40,000 yards of earth have been removed from the site and stored on property owned by Larry Hughes to use for future backfilling around the new treatment system. The old primary clarifier, trickling filter, [...]

City Requests Bids for Wastewater Treatment Plant Upgrade

The City of Salida will accept separate sealed bids at City Hall through 10:00 AM on July 15, 2011 for the upgrade of the regional wastewater treatment facility. At that time, such sealed bids will be opened and read aloud. City Hall is located at 448 E 1st Street, Suite 112. This project consists of [...]

Wastewater Safety Award, Project Update

The City of Salida Wastewater Treatment Plant Project has been advertised for bids. A mandatory pre-bid meeting was held at 10:00 A.M. on November 5, 2010 at City Hall and then at the Wastewater Treatment Plant.  There were 7 contractors in attendance, with a total of 24 people.  Bids will be received by the City [...]

From the Archive