Wastewater Treatment Plant Upgrade
Wastewater Treatment Plant Update
Wastewater Treatment Plant construction began September 28, 2011 with mobilization, excavation and demolition of old equipment. During the last four months, 40,000 yards of earth have been removed from the site and stored on property owned by Larry Hughes to use for future backfilling around the new treatment system. The old primary clarifier, trickling filter, [...]
City Requests Bids for Wastewater Treatment Plant Upgrade
The City of Salida will accept separate sealed bids at City Hall through 10:00 AM on July 15, 2011 for the upgrade of the regional wastewater treatment facility. At that time, such sealed bids will be opened and read aloud. City Hall is located at 448 E 1st Street, Suite 112. This project consists of [...]
Wastewater Safety Award, Project Update
The City of Salida Wastewater Treatment Plant Project has been advertised for bids. A mandatory pre-bid meeting was held at 10:00 A.M. on November 5, 2010 at City Hall and then at the Wastewater Treatment Plant. There were 7 contractors in attendance, with a total of 24 people. Bids will be received by the City [...]
Advertisement for bids – 2.7 MGD Wastewater Treatment Facility
Separate sealed bids will be received by the City of Salida for the construction of a 2.7 MGD Wastewater Treatment Facility. Please note that the City issued an addendum to this request for bids on November 12th to extend the deadline until 2:00 PM on Tuesday, December 9th at which time the sealed bids will … more [...]
Public Hearing: Debt Issuance for Wastewater Treatment Facility Upgrade
A public hearing will be held during the City Council Meeting on September 21, 2010 regarding the financing of a major upgrade to the wastewater treatment facility. Please see more information under the “Projects” section of this website. more »