Public Meeting 03 26 2015 on H Street Phase II

A public meeting will be held March 26, 2015 at 6:00 p.m. in the Salida SteamPlant Theatre and Event Center Ballroom to inform neighbors, adjacent businesses, stakeholders and the general public of the planned street improvements for H Street. Phase I included the improvements for 3rd to 8th Streets. Phase II will include improvements from 8th Street […]

H Street from 3rd to 8th Streets Closed Thursday and Friday, October 16th and 17th, 2014

Due to the Colorado weather plans for asphalting H Street have been delayed but good weather is in the forecast and Y&K Excavation, Inc. will be installing asphalt on H Street between 3rd and 8th Streets, on Thursday, October 16th and Friday October 17, 2014.  Third (3rd) and Ninth (9th) Streets will remain open throughout each […]

Learn about Colorado sales tax law and compliance Thursday, September 18

Do you know how much property tax you are paying to the City of Salida? You may be surprised… Zero! In 2008, the City of Salida repealed its property tax. City services depend on sales tax. We want our local businesses to thrive for … more »

3rd Street between H and I closed Tuesday, August 26 – Thursday, August 28

Y&K Excavation, Inc. will be installing storm drains across 3rd Street related to the H Street reconstruction project. Accordingly, 3rd Street between H and I Streets will be closed to accommodate the installation of the storm drain Tuesday, August 26 through Thursday, August 28. Y&K anticipates that the street will re-open on Friday, August 29. Businesses […]

8th and H Street Intersection closed Wednesday, August 20 – Friday, August 22

Y&K Excavation, Inc. has been installing water main lines and storm drains on H Street from 7th Street through 8th Street this week related to the H Street reconstruction project. Accordingly, the intersection of 8th and H Street will be closed to accommodate the installation of the water main and storm drain Wednesday, August 20 […]

7th Street from G to I Streets will be closed Friday, August 15

Y&K Excavation, Inc. has been installing storm drains on H Street from 6th to 8th Street this week related to the H Street reconstruction project. Accordingly, 7th Street from G to I Streets will be closed to accommodate the installation of the storm drain on Friday, August 15. Y&K anticipates that the street will re-open […]

H Street Reconstruction Update August 5-10, 2014

Y&K Excavation, Inc. will be installing water service lines from 6th to 8th Street on H Street this week (August 5-10, 2014). Temporary water shut offs are necessary as the houses are tied to the new line. Notification for water shut offs will be given in person (via the front door of the property) prior […]

H Street Reconstruction project update for next week, July 28-August 1

Y&K Excavation, Inc. will be installing a new storm drain from 5th to 6th Street on H Street next week (July 28th –Aug. 1st), during which the intersection of 5th and H will be closed. Y&K will also be hooking up water services from 6th to 7th Street with temporary water shut offs between 5th […]

7th Street from G to I closed through Friday, July 25

Y&K Excavation, Inc. continues to work on the installation of the new sewer line as part of the H Street reconstruction project. Installation of the sewer main will require 7th Street from G to I Street to be closed to all traffic through Friday, July 25. Y&K expects the street to re-open on Saturday, July […]

Street closure: 7th Street from G to I will be closed to all traffic Monday & Tuesday, July 21 & 22

Y&K Excavation, Inc. will be installing a sewer main on Monday and Tuesday as part of the H Street reconstruction project. Installation of the sewer main will require 7th Street from G to I Street to be closed to all traffic Monday & Tuesday, July 21 & 22. The road will re-open in the evening […]