Public Works

7th Street from G to I closed through Friday, July 25

Y&K Excavation, Inc. continues to work on the installation of the new sewer line as part of the H Street reconstruction project. Installation of the sewer main will require 7th Street from G to I Street to be closed to all traffic through Friday, July 25. Y&K expects the street to re-open on Saturday, July […]

Street closure: 7th Street from G to I will be closed to all traffic Monday & Tuesday, July 21 & 22

Y&K Excavation, Inc. will be installing a sewer main on Monday and Tuesday as part of the H Street reconstruction project. Installation of the sewer main will require 7th Street from G to I Street to be closed to all traffic Monday & Tuesday, July 21 & 22. The road will re-open in the evening […]

H Street reconstruction update for week of July 7-11

Y&K Excavation, Inc. has installed new service lines between 3rd Street and 5th Street on H Street. Water mains will be placed between 5th Street and 7th Street on H this week. Water shut offs are not anticipated this week. Residents will be notified in advance via door hangers on their front door, and in […]

H Street Reconstruction Water Shut Offs July 2nd & 3rd

Y&K Excavation, Inc. will be connecting temporary water lines to the new main water line. They will be temporarily shutting off water from 5th Street to 7th Street on H Street, from G to H on 6th Street, and from H Street to the alley on 6th Street on Wednesday, July 2 and Thursday, July […]

Advertisement for Bids: Slurry Seal Project

Sealed BIDS for construction of the 2014 Salida Slurry Seal project will be received at the City Public Works Building 340 W Highway 291, Salida, CO 81201 until 11:00 AM July 9, 2014 at which time they will be publicly opened and read. Slurry Seal quantities shall equate to approximately 20,726 square yards. Performance and Payment […]

H Street Reconstruction Update

Y&K, Inc. has installed the 8-inch water main from 3rd to 5th Street on H Street. Y&K will start connecting temporary water lines into the new permanent water main this week, June 24-June 30, 2014. During the time that the water lines are hooked to the new main there will be temporary water shut offs. […]

H Street Reconstruction Project update for week of June 16-20, 2014

Y&K Excavation, Inc. will be installing water mains from 4th to 5th Street during the week of June 16 through June 20, 2014. Y&K does not anticipate any water shut offs during the week due to the use of temporary water lines while water mains are installed. In the unlikely event of water shut offs […]

Sidewalk Cutting Resumes Monday, June 16th

Salida Public Works and Precision Concrete Cutting will resume removing hazardous sidewalks within the City limits Monday, June 16th. Crews will work east of E Street and west of G Street. Work is anticipated to … more »

H Street water outages for June 9

Y&K Inc. will be installing water mains on H Street from 3rd to 5th Streets June 9 through June 13, 2014 in accordance with the H Street reconstruction project. Water will be shut off Monday, June 9 from 8:00 a.m. to 4:00 p.m. to install main line valves. Affected will be the south side of 3rd Street […]

H Street curb and gutter slated for removal

This week, residents should expect the removal of existing curbs and gutters from 3rd to 8th Streets by Y & K, Inc., the contractor hired by the City of Salida to complete the H Street reconstruction project. Y & K, Inc. will notify any residents if any landscaping will be removed, however, Y & K, […]

Page 10 of 14« First...89101112...Last »